On December 15, 2016, the NRC issued a Notice of Violation to Romeo RIM for a Severity Level III Problem involving four violations. The first violation involved the failure to transfer or dispose of a device containing byproduct material by transfer to another general licensee as authorized in 10 CFR 31.5(c)(9), or to a person authorized to receive the device by a specific license as required by 10 CFR 31.5(c)(8)(i). Specifically, on May 24, 2016, the licensee transferred a generally licensed fixed gauge to two companies, and neither company was authorized to receive the gauge. The second violation involved the failure to assure that the generally licensed device is tested for leakage of radioactive material and proper operation of the on-off mechanism at no longer than six month intervals or at such other intervals as are specified in the label as required by 10 CFR 31.5(c)(2). Specifically, between June 1998, and July 8, 2016, the licensee failed to test the gauge for leakage and proper operation of the on-off mechanism, which is longer than the 36 month frequency specified in the label. The third violation involved the failure to appoint an individual responsible for having knowledge of the appropriate regulations and requirements and the authority for taking required actions to comply with appropriate regulations and requirements as required by 10 CFR 31.5(c)(12). Specifically, the last known responsible individual retired in 1991, and the licensee did not appoint another such individual until June 23, 2016. The effective date of this requirement was February 16, 2001. The fourth violation involved the failure to register the gauge as required by 10 CFR 31.5(c)(13)(i).